Water Updates

 

Irish Water is the new national utility body responsible for managing water and drainage operations and also water quality. It is now the contact source for the delivery of water services to homes and businesses in Ireland.  Consumers/customers with queries relating to water supply, water quality and wastewater issues need to contact Irish Water through means of the contact methods below: 

 

Contact Details for Irish Water

By Telephone: 1890 278 278 (LoCall)
By Minicom: 1890 378 378 (system for hearing impaired customers)
Website: www.water.ie
On Twitter: @IrishWater
Postal Address: Irish Water, PO Box 860, South City Delivery Office, Cork City

 

 

For information in relation to the current water situation in the Fingal Area please see page below.

Water Supply Information - Friday 20th March 2015 15.00pm

 

Fingal Area:    There are currently no reported water outages in the area.

 

 

 Swords Wastewater Treatment Plant  works on primary sludge tank - Friday 20th March


Essential maintenance on the primary sludge tank which commenced on Wednesday 18th March has now been completed.

 

 

Planned Works-Balbriggan Area Dublin Road Pumping Station & Associated Works-Updated 16th March 2015

This work is being undertaken by Jons Civil Engineering and expected to last for approximately 14 months from July 2014. Unfortunately it will be necessary to close a section of the public car park for the duration of the works and there will also be intermittent traffic disruption and possible road closures over this period. Every effort will be made to provide early notification of any such disruptions.

 The current status of works on Hamilton Road are as follows

  • One outstanding section of the new pipes to be installed on Hamilton Road requires a Gas Main diversion. Coordination of the Gas Main diversion and completion on the new Hamilton Road pipelines is currently being finalised. These works are now scheduled to be commence on Monday 23rd March and anticipated to take 2 weeks to complete.
  • Traffic Management for this work will require a shuttle system to be implented for the duration anticipated.
  • Completion of the permanent reinstatement on all sections of public road affected by the scheme is due by the first week of August 2015. The situation regarding the Permanent Reinstatement of Hamilton Road will be reviewed following completion, testing and commissioning of all pipe lines installed in this location. We expect the permanent reinstatement of Hamilton to be undertaken between April and May 2015.

  A revised information booklet is expected to be issued shortly.

 

Planned Works -Malahide Interim Drainage Scheme commenced June 2014 -Updated 15th January 2015.

Phases (1a) Church Street and (1b) Grove Road :  Reinstatement has been carried out. Relining of the double yellow lines in these areas will be carried as soon as weather permits.  Phase (2) Old Street: Work on this area is substantially complete and reinstatement is expected to commence before the end of January.   The Rising Main section to be carried out on the Back Road, Malahide is expected to commence next week (week of the 19th January) and will take 6 weeks to complete (week ending 6th March current prediction).  Reinstatement of this area will follow and as of now is expected to be complete by 16th March.  

This will be the completion of the works in putting in the service pipes, however further work will be required regarding installation of pumps.   Information on when this work commences and the timeframe of the works will be provided as soon as it becomes available.

Malahide Interim Drainage Scheme update

 

Cloghran Drainage Scheme

The Cloghran Drainage Scheme has commenced and will facilitate the areas of Cloghran, Glebe, and part of the Baskin Lane. It will also assist in the future development within this area.  Please follow link below for more details on the scheme.

Cloghran Drainage Scheme

Swords Waste Water Treatment Plant-Erection of Fencing at Newcourt Mews

Fencing has been erected on part of the open space in Newcourt Mews Estate to facilitate the construction of an interceptor pipline. The fencing will remain in place until mid 2015 to ensure the health and safety of residents and site staff while the construction works are being carried out. Construction vehicles will access the area through the Treatment Plant. When the works have been completed the fencing will be removed and the open space will be reinstated to its original condition, which will include the replanting of trees. 

We apologise for any inconvenience to residents in the area while these works are taking place.